Ar/completed Substations

66/15 KV Existing substation expansion

Location: CHAD/ N'DJAMENA, LAMADJI SUBSTATION

Client: Green Source Investments

End User: Société Nationale d'Électricité (Chad National Electricity Company)

Project Date: 2026

Scope of Work:

Civil, Electro-Mechanical works and Testing &Commissioning for Substation Bay.

Phosphate Project

Location: Jordan, Al-Karak

Client: Jordan Phosphate Mines Co JPMC

End User: Jordan Phosphate Mines Co JPMC

Project Date: 2024

Scope of Work:

Civil rehabilitation for two substations and engineering, supply and installation of steel structural warehouse.

KOSPO – HRSG #1 & HRSG #2 Chemical Cleaning -POWER PLANT

Location: Jordan , Al-Karak

Client: KOSPO

End User: KOSPO

Project Date: 2023

Scope of Work:

Participate in the shutdown activities by conducting chemical cleaning for Plant HRSGs.

CEGCO Power Plant-Root Cause Analysis

Location: Jordan, Zarqa Power Plant

Client: CEGCO

End User: AQWA

Project Date: 2022

Scope of Work:

Supply Services to Carry Out RCA Testing Pipe Failure

400 KV Attarat AIS substation- Electromechanical works, T&C.

Location: Jordan, Qatraneh

Client: Hyosung Heavy Industrial Corporation

End User: NEPCO

Project Date: 2021

Scope of Work:

Mechanical, Electrical installation & testing & commission works.

Testing and commissioning for Six MV – Substation

Location: Jordan, Amman

Client: ULUSOY ELECTRIK / ABB

End User: EDCO

Project Date: 2018

Scope of Work:

Testing and commissioning for Six MV – Substation