June 3, 2026

Completed Projects – PV Plants

66 MWP SOLAR PV PROJECT AT MAAN / JORDAN

Piling works, Electromechanical installation supervision and testing& commissioning


66/15 KV EXISTING SUBSTATION EXPANSION AT CHAD / N’DJAMENA, LAMADJI SUBSTATION.

The works include Civil ,Electro-Mechanical works and Testing &Commissioning for substation Bay.


NOOR CHAD SUBSTATION PROJECT

Electromechanical works , Tesing and commissioning for 33/66KV Substaion project.


120MWP OPERATION & MAINTENANCE CONTRACT AT ADEN / YEMEN

Coduct operation & Maintenance for 120MWp PV plant including the monthly and yearly monthly performance reports.


50MWP SOLAR PV PROJECT AT N’DJAMEN

Piling works , electromechanical installation supervision and testing & commissioning


RE-HABILITATION OF TWO SUBSTATIONS / JORDAN PHOSPHATE MINE’S / SOUTH OF JORDAN

Civil rehabilitation for two substations and engineering – supply and installation of steel structural warehousw


CONDUCTING PULL OUT FOR TWO SOLAR PLANTS AT AL-AIN / UAE

This works include pile ramming, and conducing vertical compression and horizontal pull out and issue the pull out test report.


ADEN PV PLANT POWER PLANT (120MWP)

Project Summary: Al Jabir has been awarded the contract for project management, pile drilling using our own drilling machines, and testing and commissioning.


HRSGs HP Side Chemical Cleaning – Korea Southern Power Co., Ltd./Jordan L.L.C


66MWP-Hussainyah MV cable termination & testing and commissioning works

1-1


Attarat – 400 KV substation for Electromechanical works

1-2


16MWP – Haza Testing and commissioning work

1-4


Co-water Schools EPC Solar PV plant

1


11MWP – Marriott & Sheraton Testing & Commissioning

2-5


5MWP Moutah Mechanical installation

1-6


11MW – Marriott & Sheraton PV cleaning

1-7


Iraq – GE testing & commissioning of Chemical Skid (FOTP)

1-8


Commissioning of MV switchgear at 7 substations

Protection-Relay-Testing-Large-768x1024


NADEC – 8 MWP SOLAR PV PROJECT

Nadec_01


Zulum – 10 MW SOLAR PV PROJECT

Zulum1